ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 |
Residential Schedule | 198 days | Wed 11/1/06 | Fri 8/3/07 | | 0% |
2 | General Conditions | 13 days | Wed 11/1/06 | Fri 11/17/06 | | 0% |
3 | Finalize plans and develop estimate with owner, architect | 10 days | Wed 11/1/06 | Tue 11/14/06 | General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%] | 0% |
4 | Sign contract and notice to proceed | 1 day | Wed 11/15/06 | Wed 11/15/06 | General contractor,Architect,Owner,Mortgage lender | 0% |
5 | Apply for Permits | 2 days | Thu 11/16/06 | Fri 11/17/06 | | 0% |
6 | Secure foundation permit | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
7 | Secure framing permit | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
8 | Secure electrical permit | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
9 | Secure plumbing permit | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
10 | Secure HVAC permit | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
11 | Secure miscellaneous permits | 2 days | Thu 11/16/06 | Fri 11/17/06 | General contractor | 0% |
12 | Site Work | 11 days | Mon 11/20/06 | Mon 12/4/06 | | 0% |
13 | Clear and grub lot | 7 days | Mon 11/20/06 | Tue 11/28/06 | Site excavation contractor | 0% |
14 | Install temporary power service | 2 days | Wed 11/29/06 | Thu 11/30/06 | Electric company | 0% |
15 | Install underground utilities | 2 days | Fri 12/1/06 | Mon 12/4/06 | Electric contractor,Plumbing contractor | 0% |
16 | Foundation | 30 days | Tue 12/5/06 | Mon 1/15/07 | | 0% |
17 | Excavate for foundations | 5 days | Tue 12/5/06 | Mon 12/11/06 | Site excavation contractor | 0% |
18 | Form basement walls | 5 days | Tue 12/12/06 | Mon 12/18/06 | Concrete contractor | 0% |
19 | Place concrete for foundations & basement walls | 5 days | Tue 12/19/06 | Mon 12/25/06 | Concrete contractor | 0% |
20 | Cure basement walls for 7 days | 7 days | Tue 12/26/06 | Wed 1/3/07 | | 0% |
21 | Strip basement wall forms | 2 days | Thu 1/4/07 | Fri 1/5/07 | Concrete contractor | 0% |
22 | Waterproof/insulate basement walls | 2 days | Mon 1/8/07 | Tue 1/9/07 | Concrete contractor | 0% |
23 | Perform foundation inspection | 2 days | Wed 1/10/07 | Thu 1/11/07 | Inspector | 0% |
24 | Backfill foundation | 2 days | Fri 1/12/07 | Mon 1/15/07 | Site excavation contractor | 0% |
25 | Framing | 39 days | Tue 1/16/07 | Fri 3/9/07 | | 0% |
26 | Install 1st floor joists | 5 days | Tue 1/16/07 | Mon 1/22/07 | Framing contractor | 0% |
27 | Lay 1st floor decking | 2 days | Tue 1/23/07 | Wed 1/24/07 | Framing contractor | 0% |
28 | Frame 1st floor walls | 5 days | Thu 1/25/07 | Wed 1/31/07 | Framing contractor | 0% |
29 | Frame 1st floor corners | 2 days | Thu 2/1/07 | Fri 2/2/07 | Framing contractor | 0% |
30 | Install 2nd floor joists | 3 days | Mon 2/5/07 | Wed 2/7/07 | Framing contractor | 0% |
31 | Frame 2nd floor decking | 3 days | Thu 2/8/07 | Mon 2/12/07 | Framing contractor | 0% |
32 | Frame 2nd floor walls | 5 days | Tue 2/13/07 | Mon 2/19/07 | Framing contractor | 0% |
33 | Frame 2nd floor corners | 2 days | Tue 2/20/07 | Wed 2/21/07 | Framing contractor | 0% |
34 | Complete roof framing | 10 days | Thu 2/22/07 | Wed 3/7/07 | Framing contractor | 0% |
35 | Conduct framing inspection | 2 days | Thu 3/8/07 | Fri 3/9/07 | Inspector | 0% |
36 | Dry In | 21 days | Thu 3/8/07 | Thu 4/5/07 | | 0% |
37 | Install 1st floor sheathing | 3 days | Mon 3/12/07 | Wed 3/14/07 | Framing contractor | 0% |
38 | Install 2nd floor sheathing | 3 days | Thu 3/15/07 | Mon 3/19/07 | Framing contractor | 0% |
39 | Install roof decking | 3 days | Thu 3/8/07 | Mon 3/12/07 | Framing contractor | 0% |
40 | Install felt, flashing and shingles | 3 days | Tue 3/27/07 | Thu 3/29/07 | Roofing contractor | 0% |
41 | Hang 1st floor exterior doors | 1 day | Fri 3/30/07 | Fri 3/30/07 | Framing contractor | 0% |
42 | Install 1st floor windows | 2 days | Mon 4/2/07 | Tue 4/3/07 | Framing contractor | 0% |
43 | Install 2nd floor windows | 2 days | Wed 4/4/07 | Thu 4/5/07 | Framing contractor | 0% |
44 | Exterior Finishes | 25 days | Fri 4/6/07 | Thu 5/10/07 | | 0% |
45 | Complete exterior brick | 15 days | Fri 4/6/07 | Thu 4/26/07 | Masonry contractor | 0% |
46 | Complete exterior siding | 10 days | Fri 4/27/07 | Thu 5/10/07 | Framing contractor | 0% |
47 | Utility Rough-Ins and Complete Concrete | 19 days | Tue 3/13/07 | Fri 4/6/07 | | 0% |
48 | Rough-in plumbing | 5 days | Tue 3/20/07 | Mon 3/26/07 | Plumbing contractor | 0% |
49 | Conduct rough-in plumbing inspection | 2 days | Tue 3/27/07 | Wed 3/28/07 | Inspector | 0% |
50 | Place concrete for basement floor | 5 days | Thu 3/29/07 | Wed 4/4/07 | Concrete contractor | 0% |
51 | Rough-in electrical | 5 days | Tue 3/20/07 | Mon 3/26/07 | Electric contractor | 0% |
52 | Conduct rough-in electrical inspection | 2 days | Tue 3/27/07 | Wed 3/28/07 | Inspector | 0% |
53 | Rough-in HVAC | 5 days | Thu 3/29/07 | Wed 4/4/07 | Heating and AC contractor | 0% |
54 | Conduct rough-in HVAC inspection | 2 days | Thu 4/5/07 | Fri 4/6/07 | Inspector | 0% |
55 | Rough-in communication - phone, cable, computer, alarm | 3 days | Tue 3/13/07 | Thu 3/15/07 | Electric contractor | 0% |
56 | Interior Finishes | 66 days | Fri 4/6/07 | Fri 7/6/07 | | 0% |
57 | Insulation | 21 days | Fri 4/6/07 | Fri 5/4/07 | | 0% |
58 | Place wall insulation - 1st floor | 2 days | Fri 4/6/07 | Mon 4/9/07 | Insulation contractor | 0% |
59 | Place wall insulation - 2nd floor | 2 days | Tue 4/10/07 | Wed 4/11/07 | Insulation contractor | 0% |
60 | Place ceiling insulation - 2nd floor | 2 days | Tue 5/1/07 | Wed 5/2/07 | Insulation contractor | 0% |
61 | Conduct insulation inspection | 2 days | Thu 5/3/07 | Fri 5/4/07 | Inspector | 0% |
62 | Drywall | 20 days | Tue 4/10/07 | Mon 5/7/07 | | 0% |
63 | Install drywall - 1st floor walls | 5 days | Tue 4/10/07 | Mon 4/16/07 | Drywall contractor | 0% |
64 | Install drywall - 1st floor overhead | 3 days | Tue 4/17/07 | Thu 4/19/07 | Drywall contractor | 0% |
65 | Install drywall 2nd floor walls | 5 days | Fri 4/20/07 | Thu 4/26/07 | Drywall contractor | 0% |
66 | Install drywall 2nd floor overhead | 2 days | Fri 4/27/07 | Mon 4/30/07 | Drywall contractor | 0% |
67 | Tape and float 1st floor drywall | 5 days | Fri 4/20/07 | Thu 4/26/07 | Drywall contractor | 0% |
68 | Tape and float 2nd floor drywall | 5 days | Tue 5/1/07 | Mon 5/7/07 | Drywall contractor | 0% |
69 | Paint and Wallpaper | 15 days | Fri 4/27/07 | Thu 5/17/07 | | 0% |
70 | Texture all except entry and kitchen - 1st floor | 5 days | Fri 4/27/07 | Thu 5/3/07 | Painting contractor | 0% |
71 | Paint all except entry and kitchen - 1st floor | 5 days | Fri 5/4/07 | Thu 5/10/07 | Painting contractor | 0% |
72 | Hang wallpaper entry and kitchen - 1st floor | 2 days | Fri 5/11/07 | Mon 5/14/07 | Painting contractor | 0% |
73 | Texture all - 2nd floor | 5 days | Fri 5/4/07 | Thu 5/10/07 | Painting contractor | 0% |
74 | Paint all - 2nd floor | 5 days | Fri 5/11/07 | Thu 5/17/07 | Painting contractor | 0% |
75 | Paint exterior siding & trim work | 5 days | Fri 5/11/07 | Thu 5/17/07 | Painting contractor | 0% |
76 | Cabinets | 11 days | Tue 5/15/07 | Tue 5/29/07 | | 0% |
77 | Install 1st floor - kitchen cabinets | 2 days | Tue 5/15/07 | Wed 5/16/07 | Finish carpentry contractor | 0% |
78 | Install 1st floor - master bath and guest cabinets | 2 days | Thu 5/17/07 | Fri 5/18/07 | Finish carpentry contractor | 0% |
79 | Install 2nd floor - hall bath and private bath cabinets | 2 days | Mon 5/21/07 | Tue 5/22/07 | Finish carpentry contractor | 0% |
80 | Install chair rails, crown moldings, trim | 5 days | Wed 5/23/07 | Tue 5/29/07 | Finish carpentry contractor | 0% |
81 | Finish Plumbing | 11 days | Thu 5/17/07 | Thu 5/31/07 | | 0% |
82 | Complete 1st floor - kitchen plumbing | 3 days | Thu 5/17/07 | Mon 5/21/07 | Plumbing contractor | 0% |
83 | Complete 1st floor - master bath and guest plumbing | 3 days | Tue 5/22/07 | Thu 5/24/07 | Plumbing contractor | 0% |
84 | Complete 2nd floor - hall bath and private bath plumbing | 3 days | Fri 5/25/07 | Tue 5/29/07 | Plumbing contractor | 0% |
85 | Conduct finish plumbing inspection | 2 days | Wed 5/30/07 | Thu 5/31/07 | Inspector | 0% |
86 | Finish Electrical | 8 days | Wed 5/30/07 | Fri 6/8/07 | | 0% |
87 | Complete 1st floor circuits to service panel | 3 days | Wed 5/30/07 | Fri 6/1/07 | Electric contractor | 0% |
88 | Complete 2nd floor circuits to service panel | 3 days | Mon 6/4/07 | Wed 6/6/07 | Electric contractor | 0% |
89 | Conduct finish electrical inspection | 2 days | Thu 6/7/07 | Fri 6/8/07 | Inspector | 0% |
90 | Complete communications wiring - phone, cable, computer, alarm | 5 days | Fri 6/1/07 | Thu 6/7/07 | Electric contractor | 0% |
91 | Finish HVAC | 8 days | Fri 6/8/07 | Tue 6/19/07 | | 0% |
92 | Complete 1st floor - zone 1 HVAC | 3 days | Fri 6/8/07 | Tue 6/12/07 | Heating and AC contractor | 0% |
93 | Complete 2nd floor - zone 2 HVAC | 3 days | Wed 6/13/07 | Fri 6/15/07 | Heating and AC contractor | 0% |
94 | Conduct HVAC inspection | 2 days | Mon 6/18/07 | Tue 6/19/07 | Inspector | 0% |
95 | Carpet, Tile and Appliances | 13 days | Wed 6/20/07 | Fri 7/6/07 | | 0% |
96 | Tile entry, kitchen and baths | 5 days | Wed 6/20/07 | Tue 6/26/07 | Flooring contractor | 0% |
97 | Carpet 1st floor | 3 days | Wed 6/27/07 | Fri 6/29/07 | Flooring contractor | 0% |
98 | Carpet 2nd floor | 3 days | Mon 7/2/07 | Wed 7/4/07 | Flooring contractor | 0% |
99 | Install appliances | 2 days | Thu 7/5/07 | Fri 7/6/07 | Appliance contractor | 0% |
100 | Landscaping and Grounds Work | 44 days | Fri 5/18/07 | Wed 7/18/07 | | 0% |
101 | Pour concrete driveway and sidewalks | 5 days | Fri 5/18/07 | Thu 5/24/07 | Concrete contractor | 0% |
102 | Install backyard fence | 3 days | Mon 7/9/07 | Wed 7/11/07 | Fencing contractor | 0% |
103 | Sod and complete plantings - front yard | 3 days | Thu 7/12/07 | Mon 7/16/07 | Landscape contractor | 0% |
104 | Sod and complete plantings - backyard | 2 days | Tue 7/17/07 | Wed 7/18/07 | Landscape contractor | 0% |
105 | Final Acceptance | 12 days | Thu 7/19/07 | Fri 8/3/07 | | 0% |
106 | Complete final inspection for certificate of occupancy | 2 days | Thu 7/19/07 | Fri 7/20/07 | Inspector | 0% |
107 | Cleanup for occupancy | 3 days | Mon 7/23/07 | Wed 7/25/07 | Maid service | 0% |
108 | Perform final walk-through inspection | 2 days | Thu 7/26/07 | Fri 7/27/07 | Owner | 0% |
109 | Complete punch list items | 5 days | Mon 7/30/07 | Fri 8/3/07 | General contractor | 0% |