ChadPepper.com

Construction  &  Real Estate

 

Residential Schedule

 

Pictures are in thumbnail format.  Click on any image to view a larger picture.

 

Gantt Schedule

Project Start:
Project Finish:
Wed 11/1/06
Fri 8/3/07

Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1 Residential Schedule198 daysWed 11/1/06Fri 8/3/07 0%
2
General Conditions
13 daysWed 11/1/06Fri 11/17/06 0%
3
Finalize plans and develop estimate with owner, architect
10 daysWed 11/1/06Tue 11/14/06General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]0%
4
Sign contract and notice to proceed
1 dayWed 11/15/06Wed 11/15/06General contractor,Architect,Owner,Mortgage lender0%
5
Apply for Permits
2 daysThu 11/16/06Fri 11/17/06 0%
6
Secure foundation permit
2 daysThu 11/16/06Fri 11/17/06General contractor0%
7
Secure framing permit
2 daysThu 11/16/06Fri 11/17/06General contractor0%
8
Secure electrical permit
2 daysThu 11/16/06Fri 11/17/06General contractor0%
9
Secure plumbing permit
2 daysThu 11/16/06Fri 11/17/06General contractor0%
10
Secure HVAC permit
2 daysThu 11/16/06Fri 11/17/06General contractor0%
11
Secure miscellaneous permits
2 daysThu 11/16/06Fri 11/17/06General contractor0%
12
Site Work
11 daysMon 11/20/06Mon 12/4/06 0%
13
Clear and grub lot
7 daysMon 11/20/06Tue 11/28/06Site excavation contractor0%
14
Install temporary power service
2 daysWed 11/29/06Thu 11/30/06Electric company0%
15
Install underground utilities
2 daysFri 12/1/06Mon 12/4/06Electric contractor,Plumbing contractor0%
16
Foundation
30 daysTue 12/5/06Mon 1/15/07 0%
17
Excavate for foundations
5 daysTue 12/5/06Mon 12/11/06Site excavation contractor0%
18
Form basement walls
5 daysTue 12/12/06Mon 12/18/06Concrete contractor0%
19
Place concrete for foundations & basement walls
5 daysTue 12/19/06Mon 12/25/06Concrete contractor0%
20
Cure basement walls for 7 days
7 daysTue 12/26/06Wed 1/3/07 0%
21
Strip basement wall forms
2 daysThu 1/4/07Fri 1/5/07Concrete contractor0%
22
Waterproof/insulate basement walls
2 daysMon 1/8/07Tue 1/9/07Concrete contractor0%
23
Perform foundation inspection
2 daysWed 1/10/07Thu 1/11/07Inspector0%
24
Backfill foundation
2 daysFri 1/12/07Mon 1/15/07Site excavation contractor0%
25
Framing
39 daysTue 1/16/07Fri 3/9/07 0%
26
Install 1st floor joists
5 daysTue 1/16/07Mon 1/22/07Framing contractor0%
27
Lay 1st floor decking
2 daysTue 1/23/07Wed 1/24/07Framing contractor0%
28
Frame 1st floor walls
5 daysThu 1/25/07Wed 1/31/07Framing contractor0%
29
Frame 1st floor corners
2 daysThu 2/1/07Fri 2/2/07Framing contractor0%
30
Install 2nd floor joists
3 daysMon 2/5/07Wed 2/7/07Framing contractor0%
31
Frame 2nd floor decking
3 daysThu 2/8/07Mon 2/12/07Framing contractor0%
32
Frame 2nd floor walls
5 daysTue 2/13/07Mon 2/19/07Framing contractor0%
33
Frame 2nd floor corners
2 daysTue 2/20/07Wed 2/21/07Framing contractor0%
34
Complete roof framing
10 daysThu 2/22/07Wed 3/7/07Framing contractor0%
35
Conduct framing inspection
2 daysThu 3/8/07Fri 3/9/07Inspector0%
36
Dry In
21 daysThu 3/8/07Thu 4/5/07 0%
37
Install 1st floor sheathing
3 daysMon 3/12/07Wed 3/14/07Framing contractor0%
38
Install 2nd floor sheathing
3 daysThu 3/15/07Mon 3/19/07Framing contractor0%
39
Install roof decking
3 daysThu 3/8/07Mon 3/12/07Framing contractor0%
40
Install felt, flashing and shingles
3 daysTue 3/27/07Thu 3/29/07Roofing contractor0%
41
Hang 1st floor exterior doors
1 dayFri 3/30/07Fri 3/30/07Framing contractor0%
42
Install 1st floor windows
2 daysMon 4/2/07Tue 4/3/07Framing contractor0%
43
Install 2nd floor windows
2 daysWed 4/4/07Thu 4/5/07Framing contractor0%
44
Exterior Finishes
25 daysFri 4/6/07Thu 5/10/07 0%
45
Complete exterior brick
15 daysFri 4/6/07Thu 4/26/07Masonry contractor0%
46
Complete exterior siding
10 daysFri 4/27/07Thu 5/10/07Framing contractor0%
47
Utility Rough-Ins and Complete Concrete
19 daysTue 3/13/07Fri 4/6/07 0%
48
Rough-in plumbing
5 daysTue 3/20/07Mon 3/26/07Plumbing contractor0%
49
Conduct rough-in plumbing inspection
2 daysTue 3/27/07Wed 3/28/07Inspector0%
50
Place concrete for basement floor
5 daysThu 3/29/07Wed 4/4/07Concrete contractor0%
51
Rough-in electrical
5 daysTue 3/20/07Mon 3/26/07Electric contractor0%
52
Conduct rough-in electrical inspection
2 daysTue 3/27/07Wed 3/28/07Inspector0%
53
Rough-in HVAC
5 daysThu 3/29/07Wed 4/4/07Heating and AC contractor0%
54
Conduct rough-in HVAC inspection
2 daysThu 4/5/07Fri 4/6/07Inspector0%
55
Rough-in communication - phone, cable, computer, alarm
3 daysTue 3/13/07Thu 3/15/07Electric contractor0%
56
Interior Finishes
66 daysFri 4/6/07Fri 7/6/07 0%
57
Insulation
21 daysFri 4/6/07Fri 5/4/07 0%
58
Place wall insulation - 1st floor
2 daysFri 4/6/07Mon 4/9/07Insulation contractor0%
59
Place wall insulation - 2nd floor
2 daysTue 4/10/07Wed 4/11/07Insulation contractor0%
60
Place ceiling insulation - 2nd floor
2 daysTue 5/1/07Wed 5/2/07Insulation contractor0%
61
Conduct insulation inspection
2 daysThu 5/3/07Fri 5/4/07Inspector0%
62
Drywall
20 daysTue 4/10/07Mon 5/7/07 0%
63
Install drywall - 1st floor walls
5 daysTue 4/10/07Mon 4/16/07Drywall contractor0%
64
Install drywall - 1st floor overhead
3 daysTue 4/17/07Thu 4/19/07Drywall contractor0%
65
Install drywall 2nd floor walls
5 daysFri 4/20/07Thu 4/26/07Drywall contractor0%
66
Install drywall 2nd floor overhead
2 daysFri 4/27/07Mon 4/30/07Drywall contractor0%
67
Tape and float 1st floor drywall
5 daysFri 4/20/07Thu 4/26/07Drywall contractor0%
68
Tape and float 2nd floor drywall
5 daysTue 5/1/07Mon 5/7/07Drywall contractor0%
69
Paint and Wallpaper
15 daysFri 4/27/07Thu 5/17/07 0%
70
Texture all except entry and kitchen - 1st floor
5 daysFri 4/27/07Thu 5/3/07Painting contractor0%
71
Paint all except entry and kitchen - 1st floor
5 daysFri 5/4/07Thu 5/10/07Painting contractor0%
72
Hang wallpaper entry and kitchen - 1st floor
2 daysFri 5/11/07Mon 5/14/07Painting contractor0%
73
Texture all - 2nd floor
5 daysFri 5/4/07Thu 5/10/07Painting contractor0%
74
Paint all - 2nd floor
5 daysFri 5/11/07Thu 5/17/07Painting contractor0%
75
Paint exterior siding & trim work
5 daysFri 5/11/07Thu 5/17/07Painting contractor0%
76
Cabinets
11 daysTue 5/15/07Tue 5/29/07 0%
77
Install 1st floor - kitchen cabinets
2 daysTue 5/15/07Wed 5/16/07Finish carpentry contractor0%
78
Install 1st floor - master bath and guest cabinets
2 daysThu 5/17/07Fri 5/18/07Finish carpentry contractor0%
79
Install 2nd floor - hall bath and private bath cabinets
2 daysMon 5/21/07Tue 5/22/07Finish carpentry contractor0%
80
Install chair rails, crown moldings, trim
5 daysWed 5/23/07Tue 5/29/07Finish carpentry contractor0%
81
Finish Plumbing
11 daysThu 5/17/07Thu 5/31/07 0%
82
Complete 1st floor - kitchen plumbing
3 daysThu 5/17/07Mon 5/21/07Plumbing contractor0%
83
Complete 1st floor - master bath and guest plumbing
3 daysTue 5/22/07Thu 5/24/07Plumbing contractor0%
84
Complete 2nd floor - hall bath and private bath plumbing
3 daysFri 5/25/07Tue 5/29/07Plumbing contractor0%
85
Conduct finish plumbing inspection
2 daysWed 5/30/07Thu 5/31/07Inspector0%
86
Finish Electrical
8 daysWed 5/30/07Fri 6/8/07 0%
87
Complete 1st floor circuits to service panel
3 daysWed 5/30/07Fri 6/1/07Electric contractor0%
88
Complete 2nd floor circuits to service panel
3 daysMon 6/4/07Wed 6/6/07Electric contractor0%
89
Conduct finish electrical inspection
2 daysThu 6/7/07Fri 6/8/07Inspector0%
90
Complete communications wiring - phone, cable, computer, alarm
5 daysFri 6/1/07Thu 6/7/07Electric contractor0%
91
Finish HVAC
8 daysFri 6/8/07Tue 6/19/07 0%
92
Complete 1st floor - zone 1 HVAC
3 daysFri 6/8/07Tue 6/12/07Heating and AC contractor0%
93
Complete 2nd floor - zone 2 HVAC
3 daysWed 6/13/07Fri 6/15/07Heating and AC contractor0%
94
Conduct HVAC inspection
2 daysMon 6/18/07Tue 6/19/07Inspector0%
95
Carpet, Tile and Appliances
13 daysWed 6/20/07Fri 7/6/07 0%
96
Tile entry, kitchen and baths
5 daysWed 6/20/07Tue 6/26/07Flooring contractor0%
97
Carpet 1st floor
3 daysWed 6/27/07Fri 6/29/07Flooring contractor0%
98
Carpet 2nd floor
3 daysMon 7/2/07Wed 7/4/07Flooring contractor0%
99
Install appliances
2 daysThu 7/5/07Fri 7/6/07Appliance contractor0%
100
Landscaping and Grounds Work
44 daysFri 5/18/07Wed 7/18/07 0%
101
Pour concrete driveway and sidewalks
5 daysFri 5/18/07Thu 5/24/07Concrete contractor0%
102
Install backyard fence
3 daysMon 7/9/07Wed 7/11/07Fencing contractor0%
103
Sod and complete plantings - front yard
3 daysThu 7/12/07Mon 7/16/07Landscape contractor0%
104
Sod and complete plantings - backyard
2 daysTue 7/17/07Wed 7/18/07Landscape contractor0%
105
Final Acceptance
12 daysThu 7/19/07Fri 8/3/07 0%
106
Complete final inspection for certificate of occupancy
2 daysThu 7/19/07Fri 7/20/07Inspector0%
107
Cleanup for occupancy
3 daysMon 7/23/07Wed 7/25/07Maid service0%
108
Perform final walk-through inspection
2 daysThu 7/26/07Fri 7/27/07Owner0%
109
Complete punch list items
5 daysMon 7/30/07Fri 8/3/07General contractor0%

Resources


IDNameGroupMax UnitsPeak Units
1Concrete contractor 100%100%
2Finish carpentry contractor 100%100%
3Fencing contractor 100%100%
4Masonry contractor 100%100%
5General contractor 100%600%
6Architect 100%100%
7Owner 100%100%
8Mortgage lender 100%100%
9Inspector 100%200%
10Electric company 100%100%
11Site excavation contractor 100%100%
12Electric contractor 100%200%
13Plumbing contractor 100%100%
14Framing contractor 100%200%
15Roofing contractor 100%100%
16Heating and AC contractor 100%100%
17Insulation contractor 100%100%
18Drywall contractor 100%200%
19Painting contractor 100%300%
20Flooring contractor 100%100%
21Appliance contractor 100%100%
22Landscape contractor 100%100%
23Maid service 100%100%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
3Finalize plans and develop estimate with owner, architectGeneral contractor40 hrsWed 11/1/06Tue 11/14/060%
3Finalize plans and develop estimate with owner, architectArchitect40 hrsWed 11/1/06Tue 11/14/060%
3Finalize plans and develop estimate with owner, architectOwner9.6 hrsWed 11/1/06Tue 11/14/060%
3Finalize plans and develop estimate with owner, architectMortgage lender9.6 hrsWed 11/1/06Tue 11/14/060%
4Sign contract and notice to proceedGeneral contractor8 hrsWed 11/15/06Wed 11/15/060%
4Sign contract and notice to proceedArchitect8 hrsWed 11/15/06Wed 11/15/060%
4Sign contract and notice to proceedOwner8 hrsWed 11/15/06Wed 11/15/060%
4Sign contract and notice to proceedMortgage lender8 hrsWed 11/15/06Wed 11/15/060%
6Secure foundation permitGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
7Secure framing permitGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
8Secure electrical permitGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
9Secure plumbing permitGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
10Secure HVAC permitGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
11Secure miscellaneous permitsGeneral contractor16 hrsThu 11/16/06Fri 11/17/060%
13Clear and grub lotSite excavation contractor56 hrsMon 11/20/06Tue 11/28/060%
14Install temporary power serviceElectric company16 hrsWed 11/29/06Thu 11/30/060%
15Install underground utilitiesElectric contractor16 hrsFri 12/1/06Mon 12/4/060%
15Install underground utilitiesPlumbing contractor16 hrsFri 12/1/06Mon 12/4/060%
17Excavate for foundationsSite excavation contractor40 hrsTue 12/5/06Mon 12/11/060%
18Form basement wallsConcrete contractor40 hrsTue 12/12/06Mon 12/18/060%
19Place concrete for foundations & basement wallsConcrete contractor40 hrsTue 12/19/06Mon 12/25/060%
21Strip basement wall formsConcrete contractor16 hrsThu 1/4/07Fri 1/5/070%
22Waterproof/insulate basement wallsConcrete contractor16 hrsMon 1/8/07Tue 1/9/070%
23Perform foundation inspectionInspector16 hrsWed 1/10/07Thu 1/11/070%
24Backfill foundationSite excavation contractor16 hrsFri 1/12/07Mon 1/15/070%
26Install 1st floor joistsFraming contractor40 hrsTue 1/16/07Mon 1/22/070%
27Lay 1st floor deckingFraming contractor16 hrsTue 1/23/07Wed 1/24/070%
28Frame 1st floor wallsFraming contractor40 hrsThu 1/25/07Wed 1/31/070%
29Frame 1st floor cornersFraming contractor16 hrsThu 2/1/07Fri 2/2/070%
30Install 2nd floor joistsFraming contractor24 hrsMon 2/5/07Wed 2/7/070%
31Frame 2nd floor deckingFraming contractor24 hrsThu 2/8/07Mon 2/12/070%
32Frame 2nd floor wallsFraming contractor40 hrsTue 2/13/07Mon 2/19/070%
33Frame 2nd floor cornersFraming contractor16 hrsTue 2/20/07Wed 2/21/070%
34Complete roof framingFraming contractor80 hrsThu 2/22/07Wed 3/7/070%
35Conduct framing inspectionInspector16 hrsThu 3/8/07Fri 3/9/070%
37Install 1st floor sheathingFraming contractor24 hrsMon 3/12/07Wed 3/14/070%
38Install 2nd floor sheathingFraming contractor24 hrsThu 3/15/07Mon 3/19/070%
39Install roof deckingFraming contractor24 hrsThu 3/8/07Mon 3/12/070%
40Install felt, flashing and shinglesRoofing contractor24 hrsTue 3/27/07Thu 3/29/070%
41Hang 1st floor exterior doorsFraming contractor8 hrsFri 3/30/07Fri 3/30/070%
42Install 1st floor windowsFraming contractor16 hrsMon 4/2/07Tue 4/3/070%
43Install 2nd floor windowsFraming contractor16 hrsWed 4/4/07Thu 4/5/070%
45Complete exterior brickMasonry contractor120 hrsFri 4/6/07Thu 4/26/070%
46Complete exterior sidingFraming contractor80 hrsFri 4/27/07Thu 5/10/070%
48Rough-in plumbingPlumbing contractor40 hrsTue 3/20/07Mon 3/26/070%
49Conduct rough-in plumbing inspectionInspector16 hrsTue 3/27/07Wed 3/28/070%
50Place concrete for basement floorConcrete contractor40 hrsThu 3/29/07Wed 4/4/070%
51Rough-in electricalElectric contractor40 hrsTue 3/20/07Mon 3/26/070%
52Conduct rough-in electrical inspectionInspector16 hrsTue 3/27/07Wed 3/28/070%
53Rough-in HVACHeating and AC contractor40 hrsThu 3/29/07Wed 4/4/070%
54Conduct rough-in HVAC inspectionInspector16 hrsThu 4/5/07Fri 4/6/070%
55Rough-in communication - phone, cable, computer, alarmElectric contractor24 hrsTue 3/13/07Thu 3/15/070%
58Place wall insulation - 1st floorInsulation contractor16 hrsFri 4/6/07Mon 4/9/070%
59Place wall insulation - 2nd floorInsulation contractor16 hrsTue 4/10/07Wed 4/11/070%
60Place ceiling insulation - 2nd floorInsulation contractor16 hrsTue 5/1/07Wed 5/2/070%
61Conduct insulation inspectionInspector16 hrsThu 5/3/07Fri 5/4/070%
63Install drywall - 1st floor wallsDrywall contractor40 hrsTue 4/10/07Mon 4/16/070%
64Install drywall - 1st floor overheadDrywall contractor24 hrsTue 4/17/07Thu 4/19/070%
65Install drywall 2nd floor wallsDrywall contractor40 hrsFri 4/20/07Thu 4/26/070%
66Install drywall 2nd floor overheadDrywall contractor16 hrsFri 4/27/07Mon 4/30/070%
67Tape and float 1st floor drywallDrywall contractor40 hrsFri 4/20/07Thu 4/26/070%
68Tape and float 2nd floor drywallDrywall contractor40 hrsTue 5/1/07Mon 5/7/070%
70Texture all except entry and kitchen - 1st floorPainting contractor40 hrsFri 4/27/07Thu 5/3/070%
71Paint all except entry and kitchen - 1st floorPainting contractor40 hrsFri 5/4/07Thu 5/10/070%
72Hang wallpaper entry and kitchen - 1st floorPainting contractor16 hrsFri 5/11/07Mon 5/14/070%
73Texture all - 2nd floorPainting contractor40 hrsFri 5/4/07Thu 5/10/070%
74Paint all - 2nd floorPainting contractor40 hrsFri 5/11/07Thu 5/17/070%
75Paint exterior siding & trim workPainting contractor40 hrsFri 5/11/07Thu 5/17/070%
77Install 1st floor - kitchen cabinetsFinish carpentry contractor16 hrsTue 5/15/07Wed 5/16/070%
78Install 1st floor - master bath and guest cabinetsFinish carpentry contractor16 hrsThu 5/17/07Fri 5/18/070%
79Install 2nd floor - hall bath and private bath cabinetsFinish carpentry contractor16 hrsMon 5/21/07Tue 5/22/070%
80Install chair rails, crown moldings, trimFinish carpentry contractor40 hrsWed 5/23/07Tue 5/29/070%
82Complete 1st floor - kitchen plumbingPlumbing contractor24 hrsThu 5/17/07Mon 5/21/070%
83Complete 1st floor - master bath and guest plumbingPlumbing contractor24 hrsTue 5/22/07Thu 5/24/070%
84Complete 2nd floor - hall bath and private bath plumbingPlumbing contractor24 hrsFri 5/25/07Tue 5/29/070%
85Conduct finish plumbing inspectionInspector16 hrsWed 5/30/07Thu 5/31/070%
87Complete 1st floor circuits to service panelElectric contractor24 hrsWed 5/30/07Fri 6/1/070%
88Complete 2nd floor circuits to service panelElectric contractor24 hrsMon 6/4/07Wed 6/6/070%
89Conduct finish electrical inspectionInspector16 hrsThu 6/7/07Fri 6/8/070%
90Complete communications wiring - phone, cable, computer, alarmElectric contractor40 hrsFri 6/1/07Thu 6/7/070%
92Complete 1st floor - zone 1 HVACHeating and AC contractor24 hrsFri 6/8/07Tue 6/12/070%
93Complete 2nd floor - zone 2 HVACHeating and AC contractor24 hrsWed 6/13/07Fri 6/15/070%
94Conduct HVAC inspectionInspector16 hrsMon 6/18/07Tue 6/19/070%
96Tile entry, kitchen and bathsFlooring contractor40 hrsWed 6/20/07Tue 6/26/070%
97Carpet 1st floorFlooring contractor24 hrsWed 6/27/07Fri 6/29/070%
98Carpet 2nd floorFlooring contractor24 hrsMon 7/2/07Wed 7/4/070%
99Install appliancesAppliance contractor16 hrsThu 7/5/07Fri 7/6/070%
101Pour concrete driveway and sidewalksConcrete contractor40 hrsFri 5/18/07Thu 5/24/070%
102Install backyard fenceFencing contractor24 hrsMon 7/9/07Wed 7/11/070%
103Sod and complete plantings - front yardLandscape contractor24 hrsThu 7/12/07Mon 7/16/070%
104Sod and complete plantings - backyardLandscape contractor16 hrsTue 7/17/07Wed 7/18/070%
106Complete final inspection for certificate of occupancyInspector16 hrsThu 7/19/07Fri 7/20/070%
107Cleanup for occupancyMaid service24 hrsMon 7/23/07Wed 7/25/070%
108Perform final walk-through inspectionOwner16 hrsThu 7/26/07Fri 7/27/070%
109Complete punch list itemsGeneral contractor40 hrsMon 7/30/07Fri 8/3/070%